Sioux Falls Road Work: Garfield Lane Restriction, Grange Closure This Week

South Garfield Avenue reduced to one lane Aug. 4-11 for water tie-in; South Grange Avenue closed Aug. 5 for water main work.

Key Facts

Garfield Ave. restriction start
Tuesday, August 4, 8:30 a.m.
Garfield Ave. restriction end
Tuesday, August 11, end of day
Grange Ave. closure start
Wednesday, August 5, 8:30 a.m.
Grange Ave. closure end
End of day, August 5
Contractor for Garfield work
First Rate Excavate Inc.
Crew for Grange work
City of Sioux Falls Public Works

Background

The City of Sioux Falls has scheduled two separate street construction projects this week, affecting South Garfield Avenue and South Grange Avenue. The work is part of ongoing infrastructure maintenance and improvements.

The first project involves a water tie-in at the intersection of South Garfield Avenue and West 26th Street, to be carried out by First Rate Excavate Inc. The second involves water main work on South Grange Avenue between West 18th and West 22nd Streets, performed by City of Sioux Falls Public Works crews.

Current Situation

Starting Tuesday, August 4, at 8:30 a.m., South Garfield Avenue will be reduced to one lane at the intersection of West 26th Street. The intersection will be controlled by stop signs while crews complete the water tie-in. The lane restriction is expected to remain in place through Tuesday, August 11, with work scheduled to wrap up by the end of the day.

Beginning Wednesday, August 5, at 8:30 a.m., South Grange Avenue will be closed between West 18th Street and West 22nd Street. City crews will be performing water main work in the area. Officials expect the project to be completed and all traffic control devices removed by the end of the day, allowing the road to reopen as scheduled.

Construction Schedule and Details
Location Type of Work Start End Traffic Control
South Garfield Ave. at W. 26th St.Water tie-inAug. 4, 8:30 a.m.Aug. 11, end of dayOne lane, stop signs
South Grange Ave. between W. 18th and W. 22nd St.Water main workAug. 5, 8:30 a.m.Aug. 5, end of dayRoad closed
Dates and times as reported by the City of Sioux Falls.

Impacts

Drivers traveling through either construction zone are encouraged to slow down, watch for workers and equipment, and obey all posted traffic signs. Motorists should consider using alternate routes to avoid delays.

The lane restriction on Garfield Avenue may cause delays for commuters using that route, while the full closure of Grange Avenue will require detours for local traffic. Pedestrians and cyclists in the area should also be aware of changed conditions.

Future Outlook

Scenario analysis: The possibilities below are not certain predictions.

If the projects proceed as scheduled, the Garfield Avenue lane restriction will be lifted by the end of the day on August 11, and Grange Avenue will reopen on August 5. However, weather or unforeseen utility issues could extend the timelines.

Should delays occur, the city may update traffic control measures, and motorists are advised to check local updates. Once completed, normal traffic flow is expected to resume in both areas.

Source: 973kkrc.com